SAP - MM consultation
period:
01.03.2015 - 31.12.2019
industry:
Plant engineering
Customer:
Eisenmann is a leading international supplier of systems for surface finishing technology, environmental technology and material flow automation.
The task
Cooperation while finishing the material master blueprint and also rework the concept of automatically creation of the material master. Also a concept of inheritance of sales order characteristics into the procurement process had to be raised.
The solution
We finalized the material master blueprint and fixed the needed material types and their expressions. Next the definition of the bi-directional interface with TEAMCENTER was completed. Crucial has been the classification ot the material master and the bill of materials under consideration of the change management (change master / revision levels). To maintain the transferred master data quickly a master data and planning cockpit has been defined and developped (ABAP-OO), the material status has been extended and a integration into SAP-PS was established. By this it was achieved, to release the procurement process (internal / external) quickly and to monitor the same. The impact of the not uncommon constructional changes can be realized and tracked by the disposition cockpit easily.
The highlights
- automatically created material master via TEAMCENTER interface
- automatically material master plant extension with derivation rules
- extended material status scheme
- material master and MRP cockpit
great endurance
Peter Mollekopf
SAP-Consultant
Phone:
+49 (0)8862 - 9879674
E-Mail:
peter@mollekopf.de
The consulting at Eisenmann was quit challenging, because of the detailed requirements, which were sometimes not so easy to implement. Without Dirk Walter and his great integration knowledge within the company, we couldn't have been successful in a adequate time. After such a long project runtime he showed great endurance and was always motivated, to workout the best solution for the company.