SAP-PS implementation

period: 01.02.2008 - 31.05.2011
industry: Plant engineering
Bild
Customer: Already 1972 ENVASES developed the first party keg under the former HUBER Packaging label. Since then they are world market leader in this area.

The task

The already used SAP-PS is to be integrated into the new logistic modules like SAP-MM, SAP-PM. New product development and product changes, investments and provision of product resources have to be processed and controlled by SAP - PS functionalities.

The solution

First we held some workshops to define a standard default project landscape. It consisted out of all possible involved company areas and a maximum of netplan activities and assigned functions. After the blueprint was finalized, we customized the system and trained the key user in using it.
Highlights of the implementation has been the general definition of a standard project wherby each active project is able to derivate a project netplan to achieve its goal. Smaller project may delete not needed netplan activities. We also used SAP-HR master data to assign people to their project work. PS-texts describe on each netplan activity what to do, so even new company people can orientate quickly into the internal project regularities. Also substitution rules were defined to fill out some fields automatically and by this ease the work of the project lead to setup the project correct. To confirm netplan activities SAP-CATS was customized. Also SAP-PM with maintanenace orders and equipments have bee integrated into the project system. Some reports have been build to track the project efforts and give an overview to the project lead.

The highlights

  • Integration HR (HR-reduced master), standard-WBS and -routings, PS-texts, substitutions
  • CATS for confirmations
  • integration plant maintenance orders
  • project controlling reporting